Ten Mile Creek Regional Wastewater System

The Ten Mile Creek Regional Wastewater System went into service for the first time in November 1970. This advanced wastewater collection and treatment facility provides service for an 85-square-mile service area in southern Dallas and northern Ellis Counties.   Contracting parties served by TRA’s Ten Mile Creek System include Cedar Hill, De Soto, Duncanville, Lancaster and Ferris. In excess of 110,000 citizens of these cities are served by the Authority.

The treatment plant for this system was developed on a 100-acre tract of land a short distance northeast of Ferris and had an initial treatment capacity of 6.78 million gallons per day.  In the early 1980’s substantial growth within the customer cities resulted in TRA planning and constructing treatment plant expansions.


The first, or Phase I expansion was completed in August 1986 and increased the plant’s rated capacity
to 11.5 MGD. The Phase II expansion was completed in May 1988 and increased treatment plant
capacity to 20 MGD.

Phase III construction was completed in September 1989. This construction basically involved the rehabilitation and refurbishment of the major components from the original 6.78 MGD treatment plant.

In its current configuration, the Ten Mile Creek Treatment Plant operates as two  separate  treatment trains. Components of the first train include those that were constructed as part of the Phase I construction program and of the original 6.78 MGD plant, ultimately refurbished under the Phase III construction. The second treatment        train includes the new treatment components added under the Phase II construction programs which increased the plant’s treatment capacity to 20 MGD.    Phase IV & Phase V construction projects have renovated and refurbished components of the entire plant    to provide for more efficient operation.
 


The Ten Mile Creek Plant is capable of treating wastewater to a 97 percent level of purity as compared to raw wastewater entering the plant. The system’s discharge permit specifically requires that the final discharge from the plant contain no more than 10 milligrams per liter of biochemical oxygen demand, 15 mg/l of total suspended solids and a seasonal limitation of 5 mg/l of ammonia in the winter months and 3 mg/l of ammonia in the summer months.

Each customer city owns and operates its own internal collection system which discharges into TRA’s Ten Mile Creek interceptor system. The Authority’s interceptor pipelines extend for approximately 33 miles not including parallel lines that have been added and will continue to be added to accommodate additional wastewater flows generated by growth within the service area. Flows entering TRA’s pipelines are metered so that customer cities are only charged for their pro rata share of system use and costs.

The Ten Mile Creek Regional Wastewater System has long been recognized by both state and federal regulatory agencies as one of the best treatment systems in the state. The system’s ability to consistently meet or exceed the stringent parameters of its wastewater discharge permit was further documented when it received the Gold Award from the Association of Metropolitan Sewerage Agencies every year since 1987 except 1994 and 1995 when it received the Silver Award.


Treatment Process Overview

Liquids Process

Primary Treatment—As wastewater flows enter the treatment plant, large debris and other materials are screened out to prevent damage to pump stations downstream. Following this, the raw wastewater is lifted by pumping stations to the plants’ four circular primary clarifiers. When wastewater enters the primary clarifiers the flow is slowed to permit gravity separation of solids. Solids that either float or settle are separated and removed from the wastewater stream during primary treatment. Solids remaining in the wastewater flow at this point are either suspended or dissolved and will be removed in later phases of the treatment process.

Secondary Treatment—
The treatment plant’s eight aeration basins represent the heart of the activated sludge method of secondary treatment. Through the use of mechanical aerators and compressed air diffusers, dissolved oxygen is mixed with the partially treated flows to provide oxygen for the support of microorganisms at optimal levels. The microorganisms consume the majority of the organic contaminants remaining in the wastewater.
 


The next stop for the wastewater in the treatment process is final clarification where the effluent from the aeration basins is returned to a relatively calm state. The final clarifiers allow the microorganisms to separate and settle to form a sludge blanket on the floor of the basin. The resulting effluent water becomes very clear. The sludge blanket is removed from the clarifier and sent to the thickener or returned to the front of the aeration basin in order to sustain the biological treatment

process. The microorganism population is controlled by how much of the sludge blanket is returned.

Advanced Treatment -- Effluent water from the final clarifiers next flows into the plant's eight automatic backwash sand filters where it is polished even further. These filters use silica sand to filter out most of the remaining impurities.

Effluent from the sand filters is next introduced into the plant's chlorine contact chambers for disinfection. Finally, the effluent is dechlorinated before it is discharged into Ten Mile Creek.

Solids Handling

Degritting -- When sludge is removed from the wastewater stream in the plant's primary clarifier, it is necessary to remove the accumulated grit from the primary sludge. The degritting process is accomplished by the dorrclone system and sedimentation. This procedure plays a vital role in increasing the service life of pumps downstream of this process due to the abrasive qualities of grit.

Thickening -- After mixing the primary and waste activated sludge, the thickening process is completed by bringing the sludge to a still state in the sludge thickeners so sedimentation may occur. Thickening is crucial because it reduces the water content of the sludge and thereby reduces the total volume requiring further processing.
 


Digestion -- Thickened sludge from the gravity thickener is next processed in four anaerobic digesters. The digestion process breaks down the organic content of the sludge into stable compounds. Methane gas produced during the digestion process is recovered and used as fuel for the boilers which maintain the digesters at an optimal operating temperature.

 

Sludge Lagoons -- Approximately 35 acres adjacent to the treatment plant store the inert digested sludge in three separate cells created by levees. Liquid from the digested sludge is decanted from the lagoons and gravity flows back to the head of the plant for treatment, leaving the residual fully treated sludge to dry. Dried sludge is disposed of in a landfill.

Surface Disposal Cells -- Approximately 25 acres adjacent to the treatment plant store the inert digested sludge in three separate cells created by levees. Liquid from the digested sludge is decanted from the surface disposal cells and gravity flows back to the head of the plant for treatment, leaving the residual fully treated sludge to dry. Dried slug is disposal of in a landfill.

Trinity River Authority of Texas
Ten Mile Creek Regional Wastewater System
(972) 225-3462