|
Lake Livingston Dam Repair Substantially Complete
Livingston, Texas-The repair to the upstream
slope protection, or large rock surface called rip
rap, on the northern face of Lake Livingston Dam is
substantially complete, ahead of schedule. The
original projected date for substantial completion
was June 15, 2006.
This will
allow the Trinity River Authority of Texas to begin
impounding water above elevation 127 feet mean sea
level (msl). TRA held the lake at this level for
the repair. How long it will take to restore the
lake to its normal elevation of 131 feet msl will be
determined by rainfall and runoff in the 16,580
square miles of the Trinity River watershed upstream
of the dam.
TRA
General Manager, Danny F. Vance said, “We sustained
some of the most severe and extensive damage that
has ever been witnessed on the upstream slope of a
structure like Lake Livingston Dam. Being in a
position to capture rainfall from runoff this early
in the normally wet spring season,” he continued, “
may enable us to restore the lake level in advance
of summer.”
On
September 23, winds on the back side of Hurricane
Rita produced a storm surge and waves that stripped
the rip rap, or large rock protective covering, from
approximately 11,000 feet of the approximately
13,700 foot long earthen embankment. When the
damage was discovered in the middle of the storm,
TRA immediately implemented its state certified
emergency action plan and began to lower the lake
level at the peak rate of 80,000 cubic feet per
second, in order to minimize further damage.
The repair was a logistics challenge for the prime
contractor, Archer Western Contractors, Ltd. The
task involved the movement of 72,215 tons of 32-inch
rock in 3,183 truckloads, and 15,808 tons of 8-inch
bedding rock in 687 truckloads. The rock was mined
from a quarry in Navarro County near Corsicana.
Full
completion of the repair calls for the restoration
of the single lane roadway on the top of the
structure. The original roadway was destroyed by
the heavy equipment and rock trucks used to replace
the rip rap. It should take approximately one month
to complete this work and will not require a lowered
lake level.
Lake Livingston represents approximately
72 percent of the city of Houston’s available water
supplies. The city has continued to use water from
the lake during construction and will increase the
volume used as the hot, dry summer conditions take
hold.
For more information contact John Jadrosich or Debbie
Bronson at (817) 467-4343
|