|
Record Rainfall and Severe Flooding Causes
Wastewater Spill in Ten Mile Creek
Arlington - High
velocity floodwater in Ten Mile Creek in southern
Dallas and northern Ellis County causing major
erosion, resulted in the collapse of creek banks and
undermining of two sections of a 39-inch pipeline
located near the creek bank. This pipeline
transports wastewater to the Trinity River
Authority’s Ten Mile Creek Regional Wastewater
System treatment plant. The creek bank failure
caused two sections of the pipeline to separate
during the morning of July 1.
The eroded creek
bank had been discovered by TRA on June 30 and the
Authority had already directed a contractor to
stabilize the pipeline. Before the contractor could
move heavy equipment to the site to shore up the
creek bank, approximately 16-feet of pipeline
separated and collapsed into the creek.
At the location of
the failure, the pipeline was transporting the
wastewater flows from portions of Cedar Hill, DeSoto,
Duncanville, and Lancaster, along with an even
larger volume of storm water.
It has been
estimated by TRA that a total of 1.89 million
gallons of wastewater spilled into Ten Mile Creek
before the outflow was stopped. The impact of this
inadvertent spill was minimized by high floodwater
in the creek, which during the ten plus hours of the
overflow the creek flow ranged from a low of 70
million gallons per day to as high as 150 MGD,
significantly diluted the untreated wastewater.
TRA constructed a temporary cofferdam to contain flow escaping from the
broken line. The line was plugged upstream and
downstream of the failure in order to completely
eliminate flow into the creek. Crews worked through
the night Thursday to complete the repair. Work will
continue today to restabilize the creek bank.
Portions of the flow from Cedar Hill were diverted to another Authority
treatment plant, which reduced the volume of
wastewater. Diversion of the remaining flow was made
to a second nearby pipeline, as quickly as possible,
while repairs were underway.
TRA began taking water quality samples to document conditions below the
broken line immediately after the incident began. No
impacts on water quality or fish and wildlife are
expected to result from this spill because of the
flooded condition of Ten Mile Creek that diluted the
spilled wastewater.
Wastewater pipelines are built adjacent to streams
and creeks to take advantage of gravity flow,
instead of relying on lift stations and pressurized
pipelines that require huge amounts of power to move
water. TRA routinely monitors its pipelines during
major rain events because of their proximity to
creeks and had discovered creek bank erosion in the
area the day before. Many erosion problems along Ten
Mile Creek have been detected and stabilized prior
to line failure during the 34-years this regional
wastewater system has been in service.
FOR MORE INFORMATION CONTACT JOHN
JADROSICH, TRA PUBLIC INFORMATION OFFICER AT (817)
467-4343.
|